Projects
Crescent Bar On-Island Construction
/Owner: Grant County PUD
Stevens Pass Mountain Resort Expansion
/Owner: Stevens Pass Mountain Resort, LLC
Engineer: RH2 Engineering, Inc.
Wells Hatchery Modernization
/Project Owner: PUD No. 1 of Douglas County
Engineer: HDR Engineering
At Azwell Wells Dam on Columbia River, project involves complete reconstruction of dam's antiquated fish hatchery. Hurst crews installed bypass waterlines, demolished old raceways, and installed new utilities systems for facilities to be constructed by general contractor, Lydig Construction.
Upper Bluff Street Improvement Project
/Owner: Town of Winthrop
Engineer: SCJ Alliance
Commercial Street - 3rd St. to 8th St. Reconstruction
/Project Owner: City of Leavenworth
Engineer: TD&H Engineering
This includes removal of existing ACP, installation of new curb, gutter, heated sidewalks, ramps, crosswalks; stormwater system, replacement of water mains, new hydrants, pedestrian lighting, streetscapes and widened, paved roadway and new parking at the Waterfront Park access.
Rocky Reach Trail
/Project Owner: Washington State Parks and Recreation Commission
This project is located along the east side of the Columbia River, north of the Odabashian Bridge in Douglas County, Washington. The project work consisted of constructing a new shared use paved trail, concrete box culvert and all related appurtenances. As of May 18, 2015, Hurst entered the final stages, involving landscaping and signage, toward completing this last phase of a large trail project, "Complete the Loop," a goal set by the community nearly 20 years ago.
No. 1 Canyon Water Facility
/Project Owner: Chelan County
Harrison Creek Side Channel - Entiat River
/Project Owner: Chelan County Natural Resource Dept.
Frazer Creek Bridges
/Consulting Engineer: Jay Kidder, P.E., Chinook Engineering
Project Owner: Methow Salmon Recovery Foundation
This emergency work involved replacing five culverts with prefabricated bridges along Frazer Creek. Due to the Carlton Complex Fires, the land owners along Frazer Creek experienced unforeseen flooding on their properties adjacent Frazer Creek; some driveways were completely washed out. The project involved a significant amount of dewatering of the stream, removal of existing culverts, removal and stream channel construction with angular shot, river rock and boulders, and placement of the prefabricated bridges.
Chikamin Creek Bridge
/Project Owner: Chelan County
23rd St NE, East Wenatchee
/Project Owner: Douglas County
Ephrata Municipal Airport
/Project Owner: Port of Ephrata
Johnson Avenue, Chelan - SR150 Improvements
/Project Owner: City of Chelan
Bradley Street South, Chelan
/Project Owner: City of Chelan
Campbell's Glen
/Engineer: Torrence Engineering
Parke Creek Barrier Removal
/Project Owner: Kittitas County Conservation Dist.
Nason Creek - Lower Oxbow Connection
/Project Owner: Chelan County Natural Resource Dept.
This contract provided for the improvement of habitat on Nason Creek off of US2 by reconnecting relic Nason Creek channels. The work included excavation and grading for and the installation of a road to allow crew access to the site of construction of two 89-foot long railroad bridges and 24 h pilings. Three coffer dams (100’, 100’, 90’) were constructed along with structure to provided passage over the dams, installation of in stream structures including placements of woody debris, placement of live stakes, placement of ELJs and grade control ELJs, boulders, boulder weirs and roughened channel, placement of gravel associated with structure placement and salmon and forage fish spawning gravel restoration work. Three large culverts were removed and excavation and construction of a 220-foot long connector channel between the bridges occurred along with the construction of permanent access roads – one at 220 feet long at the upstream end of the project and the other, 1,650 feet long at the downstream end of the project followed by restoration of plantings and other natural habitat. This is the first known project where BNSF has collaborated with the BPA, the provider of funding.